Newsletters
|
 |
Project Overview: The Upper Grass Lake Sewer Pipe Rehabilitation project rehabilitated a failing sewer main on the Upper Grass Lake Sewer Pipe, located on 14th Avenue. The Percival Street Sanitary Sewer Pipe Rehabilitation rehabilitated a failing sewer main on Percival Street between Madison Avenue and Garfield Street. The Lilly Road Sanitary Sewer Pipe Rehabilitation - Phase 2, rehabilitated a failing sewer main between Ensign Road and Martin Way, this included the intersection at Martin Way.
Project Information: To rehabilitate the pipe, a Cured-In-Place-Pipe (CIPP) method was used. For more information on this process check out our newsletters!
Next Steps: Construction on both projects began on Monday, June 30, 2008. Construction took two to three days and is now complete.
Traffic Impacts: The roadway remained open throughout construction on all projects.
Questions?
If you have questions or would like more information regarding these projects, contact Tim Richardson, Project Manager, at (360) 753-8749 or by e-mail.
Need More Information about Public Works Programs or Services? Contact the Public Works office.
- Physical Address: 924 7th Ave. SE, Suite A
- Mailing Address: PO Box 1967, Olympia, WA 98507
- Download printer-friendly (PDF) directions to our office
- Hours: M - F from 8 a.m. to 5 p.m. (except for City-recognized holidays)
- Phone: (360) 753-8588
- TTY: (360) 753-8270
- Email: Public Works